|
DIRECT RAILWAY LINE DAMMAM - RIYADH
The need for an efficient transportation
system in the Kingdom of Saudi Arabia was recognized at the beginning of the
1970's at which time the country's great economic growth gave way to a very
large increase in transportat ion demand which constantly surpassed the supply,
especially in the more important areas like the strip which extends
approximately 450 km. between the Capital, Riyadh and Dammam, the main Saudi
Arabian port on the Persian Gulf. This
led the Saudi Arabian Government to concentrate the nation's financial
resources on the development of transportation systems which required
short-term realization times, like the highway and airline systems, penalizing
in this manner the development of the railway network.
It was only toward the mid 1970's that
following a change in interest for the railway sector, the S.R.O. began to
understand the need to give new energy to the sector through the process of
reorganizing the existing infrastructural assets and through the construction
of new railway lines.
Therefore, following the contract to carry
out the executive project and supervise the works to overhaul the existing
Dammam-Hofuf-Harad-Al Kharj-Riyadh railway, the S.R.O. also entrusted Technital
with the task of conducting the feasibility study, the preliminary and final
designs and supervision of the works for the new direct railway line between
Dammam and Riyadh which would shorten travel time considerably with respect to
the existing line through Harad and Al Kharj.
An in-depth and complete analysis of the
transportation within the Dammam-Riyadh corridor was done, also by evaluating
the convenience of starting a direct high speed (250 km/h) connection for
passenger service. The study began with the preparation of a 1:250.000 scale
map and identification of five possible alternatives.
Successively, based on the traffic data
collected, and on-site inspections done along
the different alternative routes, two possible hypotheses for
intervention were chosen for comparison in the economic analysis :
-
connection between Dammam and Riyadh through Hofuf (alternative no. 1)
- a
direct connection between Dammam and Riyadh
(alternative no. 2)
Based on the data collected, a graph of the
transportation system associated with each alternative was developed. Through
the same mathematical model, the demand for transportation within the system
was then assigned, also by simulating the volume of freight and passenger
traffic in the year 2000 based on various hypotheses of growth in transport
demand. Each alternative was
subbsequently developed on the preliminary design level by defining the
technical and operating standards of the new railway line and the related
investment, operating, and maintenance costs.
Cost breakdowns were then elaborated and, through comparison with the
opportune system of general reference, the benefits associated with each
alternative and the relative economic indexes were defined.
Upon
termination of the economic analysis and in agreement with the S.R.O.,
alternative no. 1 was chosen, envisaging a single-track line
Dammam-Hofuf-Riyadh which, flanking the existing railway in the stretch between
Dammam and Hofuf, in fact doubles it.
The final design which followed the
feasibility study was divided into the following work phases :
- aerophotogrametric survey of the terrain
followed by a topographic survey for the identification, staking and benchmarking of the photograms
and subsequent mapping;
- geophysical and geotechnical surveys on
the nature and bearing capacity of the terrain and the availability of borrow
pits for construction materials.
Particular attention was paid to defining the influence that the
presence of quicksand and vast deposits of sulphate sand (sabkhah) could have
on the infrastructure;
- hydrological and hydraulic study;
- preparation of the final design which
included the definition of the horizontal and vertical lay-out of the
structure, the permanent way and all of the other elements comprisaing the
railway infrastructure;
- preparation of the tender documents for
the construction of the railway line.
The final alignment of the railway line
originated from the necessity to guarantee the most direct connection possible
between Dammam and Riyadh while taking into consideration the various
constraints which could effect it.
Therefore, for the section between Dammam and Hofuf, the lay-out
followed the existing railway line, whereas in the section between Hofuf and
Riyadh the lay-out was conditioned by :
- constraints of a
geomorphological nature related to crossing
the Dhana desert;
- constraints deriving from the crossing of the areas where
petroleum is extracted;
- constraints deriving from the presence of military zones;
- constraints linked to the necessity to run the route through the
city limits of Riyadh.
The railroad was designed for a
diesel-electric traction system with standard 1,435 mm. rail gauge, a project
velocity of 150 km/h, and a maximum axial weight of 22 tons (locomotive) and 25
tons (wagons). The horizontal curve
radius was set at a standard measure (2500 and 5000 m.), when possible.The
minimum radius in straight stretches is 2000 m. and 1750 m. in the sections
between Hofuf and Riyadh and Dammam and Hofuf respectively. The maximum gradient is 10 per 1,000
(non-conpensated). The total length of
the line is 449 km.
The location and number of stations along the
line were defined to serve the major inhabited areas, as well as the areas of
special interest, and to guarantee an adequate level of railway capacity in
relationship to the amount of traffic expected. Four intermediate stations were planned between Dammam and Hofuf
and seven between Hofuf and Riyadh.
The permanent way was built with U/C 60 rails
which were continuously welded between
stations. The sleepers are of
the monobloc p.r.c. type which were produced locally in two new plants built in
Riyadh and Hofuf, for which the
installation and production tests were followed by Technital on behalf of the
S.R.O. The coupling devices are the
indirect elastic type (Pandrol and Vossloh).
The switches are U/C 60 type with a 1/12 tangent (on the railway line), 1/9 (at stations),
and 1/7.5 (in freight yards).
The track formation has an overall width of
7.69 m. on embankments and 17.6 m. in trenches, in that two 5 m. lateral paths
were planned to enable transit of maintenance vehicles and to protect the track
from slopes. A layer of a granular mixture
of subballast was also foreseen in the composition of the superstructure.
Lastly, a special effort was required for the
protection of the railway in crossing the areas of quicksand and sabkhah.
In
the first case, sand slopes with a slight gradient (1:4) were utilized and were
stabilized with a series of superimposed layers of compact granular mix
(protective windrows). In cuttings, ample,
adequately shaped sections were planned in order to halt the advance of the
dunes. In the second case, protection
of the sabkhah was obtained through the use of non-woven fabric and preloading
of the embankments. The aggression of
the sulphate of the sabkhah on the concrete elements cements was controlled
through the use of sulphate-resistant cements, of waterproof cements produced
with a low water/cement ratio, and of superfluidizers to keep the mix in good
working order, even in a hot climate.
The hydological survey led to dividing the
territory crossed by the railway into three areas, each one characterized by
its own rainfall pattern. Therefore,
the three distinct equations of climatic probability were elaborated first,
even if the equation relative to the zone of the highest precipitation was
later considered opportune for all three zones. Based on the rainfall data collected from the Saudi Arabian
Ministry for Agriculture, as well as specific site surveys, the maximum flow
rates were calculated, on the basis of which
the hydraulic works were then dimensioned.
The structures
foreseen in the project were located in the Hofuf-Riyadh section and include a
total of six bridges and two viaducts
for an overall length of 2,150 m.
Considering the rather difficult environmental conditions and the
difficulty in transporting heavy loads along the route, utilization of
structures in prestressed, precast concrete were used at the base of the works
and then launched. All of the
construction works were planned in view of the possibility of doubling the
Hofuf-Riyadh line with the purpose of reducing future interruptions to railway
operations to a minimum.
|