|
NAVIGATION
& MARINE HYDRODYNAMIC STUDIES
Breakwaters at the entrances of the ports of the Venice Lagoon - Italy
Client:
Venezia Nuova Consortium - Ministry of Public
Works
Services:
Ports entrance studies, hydrodynamic and wave propagation
studies; assistance to model testing;
preliminary and detailed
design; general supervision.
Period: 1991
- 1997
Construction cost:
€
71,787,500
The project:
The construction of the six breakwaters at the entrances of
the three ports of the Venice lagoon, Chioggia, Malamocco and
Lido, which was carried out in the period between the
mid-nineteenth century to the early twentieth century, was
motivated by the need to protect the lagoon's navigable access
channels against filling with sediment. These works did in
fact cause an increase in the depth of the access channels,
but at the expense of the stability of the breakwaters which
increased proportionally with the depth.
Technital was commissioned by the Venezia Nuova
Consortium to:
-
examine
the reasons for the continuous maintenance
requirements;
-
evaluate the feasibility of definitively rehabilitating
the breakwaters, in relation to their present and future
function;
-
suggest the best type of intervention;
-
perform the preliminary and detailed design of the
proposed interventions.
The Preliminary Design, completed in 1991, included the
examination and development of the types of intervention
needed to make the breakwaters compatible with their present
use and, above all, with their future function, when the flood
control works (the fixed works for the mobile barriers) have
been constructed.

These interventions comprise:
-
the creation of a filter in the lower part of each
breakwater which prevents the loss of fine materials, without
removing all or part of the existing claddings and thus without creating
hazardous conditions for the overall stability;
-
the creation of a protection against erosion at the base
of the breakwaters to combat further subsidence of the
foundations;
-
the renovation of the claddings exposed to current
and wave motion action, using similar materials to the
existing ones the restoration of the crown wall.
During 1992-1997 TECHNITAL
developed the Detailed Design for all six breakwaters at the
port entrances. The work defined by the design comprises:
-
the installation of filters by the laying of 20-150 mm.
crushed stone and foundation berms for the cladding by laying
50-1000
kg. and 1-3 t. rubble for a total of 1,500,000 t.
-
the restructuring of the protective cladding by
installing 6.3 m3 tetrapods,
with a total of 40,000 m3 of
concrete, and of 2-5 t.
rubble for a total of about 300,000 t.
This Project includes the reconstruction of 6 breakwaters at
the 3 lagoon port entrances on depths varying from 9 to 19 m,
for a significant wave height of 5,5 m, and for a total length
of approx. 6,200 m.
-
Back to Navigation & Marine
Next Project >>
|