|
COASTAL DEFENCE WORKS
Mobile surge barriers at the three inlets of the Venice lagoon
- Italy
Client: Venezia
Nuova Consortium - Ministry of Public Works
Services:
Basic, Preliminary, and Detailed Design of flap-gate
barriers at the lagoon inlets of Chioggia, Malamocco, S.
Nicoḷ di Lido and Treporti and all related marine,
electro-mechanical and civil works.
Period:
1987-1992, 2000-in progress
Construction cost:
€
2,296,225,700
The project:
The works at the lagoon inlets for the defence of Venice and
its lagoon from tidal flooding represent one of the largest
hydraulic engineering projects of our times.
The optimal solution to solve this problem, as identified by
the Preliminary and Basic Design phases, is the construction of
four fixed barriers with buoyancy flap-gates, two at the Lido
mouth, one at the Malamocco mouth and one at the Chioggia
mouth, with the following dimensions:
• Lido S.Nicoḷ: width 400m., depth 11m., 20
flap-gates
• Lido Treporti: width 420m., depth 6m., 21 flap-gates
• Malamocco: width 400m., depth 15m., 20
flap-gates
• Chioggia: width 360m., depth 11m., 18
flap-gates
Each flap-gate will consist of a rectangular metal caisson, 20
metres wide, 4 metres high and of variable length depending on
the depth of the canal.
The four sets of buoyancy flap-gates, with an overall length
of almost two kilometres, will be anchored to pre-cast
concrete foundation caissons floated to the site place and
laid in special trenches, and will be raised by the
introduction of compressed air during exceptional tidal
conditions to prevent the lagoon from flooding.
Refuge basins, with navigation locks for small and medium
sized craft, will allow the harbouring and transit of marine
traffic even when the flap-gates are raised.The
design of the refuge basins and their connection with the
mobile works and that of the locks for small craft involved,
in addition to the hydrodynamic and wave motion model
studies and the traditional dimensioning, the use of
models for simulating the successive arrival of craft and
models for the access and evolution manoeuvres within
the internal basins.
The preliminary design of the work at the inlets was performed
by Technital during 1990-1992, with the co-operation of
numerous specialised national and international institutes
which, under the designer's co-ordination, carried out
innumerable tests on physical models, studies with
mathematical models and measurement campaigns.
Following the analysis of the results of the physical and
mathematical model tests and of those derived from monitoring
the full-size experimental module (MO.S.E.), the "heart" of
the system , the buoyancy flap-gates, were designed.
The definition of the functional and structural dimensions,
the selection and scaling of special components and of the
corrosion protection system, and the definition of the
tolerances on the basis of the construction methods to be used
were performed separately for each inlet.

The dimensions of the principal structures of the barrier were
then defined: these include the flap-gate housings, the fixed
works on either side of the barriers, the gantry crane
shelters and the control building. Since these are the only
above-ground structures of the complex, a special study was
carried out for their insertion in the environment resulting
in the definition of singular architectural solutions for the
buildings, compatible with local morphology and the historical
tradition of the city. By means of mathematical solutions of
the problems of building-ground interaction, the related
settlements and the safety coefficients for various
alternative solutions, a type of foundation was selected
consisting of caissons pre-cast off-site and sunk in situ with
flexible watertight joints.
The design of the bottom protection, the auxiliary technical
plants and the study of the most suitable realisation stages
in relation to the construction methods and to minimal
interference with the anthropic activities concluded the
design activities.
Back to Coastal Defense Works
Next Project >>
|