|
INDUSTRIAL & COMMERCIAL
PORTS
Industrial Port of Ras Laffan - Qatar
Client: Condotte
& Partners for Qatar General Petroleum Corporation (Q.G.P.C.)
Services: Hydrodynamic
and navigational mathematical model studies,
Preliminary Design of port layout, Basic,
preliminary
and detailed design of the main breakwater preliminary
design of the jetties, Environmental
impact studies.
Period: 1991
- 1994
Construction cost:
€ 694,118,000
The Project:

The port of Ras Laffan, which was completed in 1995, is at
present the most important LNG vessel in the world.
The design and construction of the Industrial Port of Ras
Laffan, included:
Construction activities were successfully completed in 1995,
ahead of schedule.
-
TECHNITAL was awarded a Contract by Condotte Qatar JV, the
nominated Contractor, for the performance of the following
engineering services:
-
review of the preliminary design of the layout;
- review of the preliminary design of the main
and lee breakwaters;
- review of the preliminary design of the access
channel and of the dredging works;
- basic and preliminary design of quay walls and berths
- basic, preliminary and detailed design of the main
breakwater .
These activities involved the execution of studies with
hydrodynamic and navigational mathematical models and the
preparation of specifications and supervision of execution
of physical model for the optimisation of the layout and
2 and 3 dimensional physical models for the design of the
breakwater.
The
layout was selected by comparing several alternative
solutions (developed starting from the solution shown in the
Master Plan), by means of a "weighted" comparison of the
behaviour of the following indicators:
-
"downtime"
due to wave motion at the berths;
-
"downtime"
due to access difficulties along the canal;
-
the
balance between dredged material and material needed for
implementation, by filling, of the harbour yards;
-
the
rationality of the access to the various harbour terminals;
-
the
possibility of further development of the port.
The Layout Design also included studies aimed at assessing
the environmental impact of the new port, such as the
variations in the littoral drift and the interference with
the discharge outlets of industrial plants, due to the
considerable hydrodynamic changes.
The Preliminary Design of the breakwaters was performed in
close collaboration with the construction contractors. It
also involved the programming and co-ordination of tests on
a two-dimensional physical model. Since a part of the
breakwater core was constructed using dredged material with
a very fine granulometry, particular care was taken over the
design and checking of the filtering layers.
The
cladding was constructed using Antifer blocks of sizes
varying from 1.9 to 4.5 cubic metres.
The Preliminary Design of the jetties also made use of the
results of model tests, in this case of a 3-D hydrodynamic
model, where the propagation of the wave motion was
reproduced and the strains at the moorings were measured.
|