|
Main Viaducts
The design and subsequent
construction of long-span viaducts along the Messina-Palermo motorway belongs to
the
second period of the works, after the removal of the block on financing to
the motorway sector, which lasted from 1975 to 1983.
In this period
new and modern construction techniques were developed which greatly reduced the
construction times for long-span viaducts and offered good guarantees in
relation to the quality of the materials used. The original design was thus
revised, introducing the solution of long-span viaducts (70-100 m) for crossing
the more difficult valleys, instead of the traditional solution of supported
girders and decks (maximum span 30-35 m), which had been widely used in the
first construction period 1967 - 1975.
One important
benefit derived from the adoption of the new type of long-span viaduct was the
reduced visual impact, the so-called “barrier effect” - due to the apparently
lighter, slimmer structures. It also proved an advantage in the numerous
geologically difficult areas because of the
reduction in
the number of supporting structures and consequent foundation works. The
environmental impact was further mitigated by the extensive landscaping works to
mask the retaining and supporting structures.
The main
elements comprising the viaduct are the following:
Deck:
Continuous caisson structure built with pre-cast interlocking ashlars launched
from the piers. The continuous deck structure eliminates the need for
intermediate joints and improves the stability of the structure.
Piers:
Two different types of piers are used according to their height:
-
piers
not exceeding 20-25 m in height have an octagonal section with maximum
dimensions of 3.50x3.50 m, broadening at the top to form a square support
(5.40x5.40 m)
-
piers of more
than 235 m in height have a square section diminishing from base to top to
arrive at a square support of 5.40x5.40 m.
Both types are
aesthetically pleasing and can be satisfactorily merged into the environment.
Lo ngitudinal and transversal seismic checks:
The longitudinal seismic forces in viaducts are concentrated in a well-defined
area, usually one of the two abutments. Since the impact of a longitudinal
tremor on a rigid structure would be disastrous, oleo-dynamic shock absorbers
are interposed between the deck and the abutment at one end while the other end
is left free to move longitudinally without constraints or elastic parts.
Support systems: During
construction the stability of the structure is guaranteed by hydraulic jacks
which can protect against the effects of unequal loading due to the weight of
the ashlars, the reaction of the launching cranes, or adverse weather
conditions. The permanent bearings, two at each bearing point, are made of
steel and teflon with an encapsulated neoprene cushion and are
multi-directional, transmitting the transversal and longitudinal stresses to the
appropriate checks and shock absorbers.
Joints:
The continuous deck system allows
the elimination of intermediate joints and the concentration of expansion joints
(designed to absorb seismic events) mainly at the abutments. These expansion
joints which are of suitably impermeabilized bridge plate type, are therefore
capable of resisting the movements transmitted by the lateral shock absorbers,
due to thermal expansion, shrinkage and fluage, coherent with the bearings.
Inspectionability:
Manholes located at the piers and abutments permit access inside the deck
caissons and the inspection of their entire length. Special openings in ashlars
on top of the piers give access from the caisson to the top of the piers for the
inspection of the support systems. At the abutments it is possible to inspect
both the supporting systems and the shock absorbers. By means of an opening at
the base of each pier and an inside ladder, the piers can be fully inspected.
Square section piers also have a manhole
allowing the inspection of the bearings and transversal checks. These piers are
therefore accessible from the pier base and from the abutments.
Rainwater runoff:
A system of gulleys and down-pipes located at each pier allow for surface
runoff. The down-pipes convey the rainwater, inside each pier, to a trap at the
pier base. As for the road formation, therefore, the rainwater can be channelled
into the local streams.
Viaduct
construction techniques
In situ
casting of the ashlars, their joining and storage:
The ashlars
comprising the deck are usually pre-cast close to the site of construction. A
single metal caisson is used, with an average production of one ashlar per day.
In the case of the Vallone Marzo viaduct, the pre-cast ashlars underwent a long
seasoning period (about a year) as the tunnel connecting their manufacturing
site and the construction site was unusable Loss of tension and shrinking due
to fluage as a result of this seasoning period was taken into consideration in
the design.
Construction of the piers:
The construction of the
piers is perhaps the simplest part of the whole construction job. The piers are
placed on the foundations in the shaft and have a box section which is built up
from the base by means of rampant caissons.
Assembly of the
ashlars:
The ashlars are assembled alternately, starting with the end one on the
piers. The faces to be joined are painted with epoxy resin and are fastened
temporarily to the ashlars already in place by means of p.r.c. steel bars. At
the end of the assembly process the closing ashlar is placed and the lower
pre-stressing cables are threaded in.
Tensioning of
the pre-stressing cables and their injection:
This is the last operation to be carried out and is highly complex due to the
fact that the hyperstatic pre-stressing reactions must be controlled as they are
induced during the tensioning process. A system of oleo-dynamic hydraulic jacks
was used to guarantee the stability of the supports during these operations so
that the necessary adjustments could be made through to an advanced construction
phase. It was thus possible to remedy at least in part any construction
inaccuracies. On completion the load is transferred to permanent steel-teflon
supports.
The following table bears witness to
the number of major viaducts on the motorway alignment, with reference to the
second construction period.
|
Name |
Length |
Number of spans
(Palermo direction) |
Number of spans
(Messina direction) |
|
Ramosa |
217.60m
+ 147.60m |
no. 2 X
38.80m + no. 2 X 70m |
no. 2 X
38.80m + no. 1 X 70m |
|
Caporale |
131.40m
+ 104m |
no. 2 X
33.20m + no. 1 X 65m |
no.1 X
70m + no. 2 counterweights of 17m |
|
Lauro |
2 X
357.60m |
no. 2 X
38.80m + no. 4 X 70m |
no. 2 X
38.80m + no. 4 X 70m |
|
Periano
|
2 X
287.60m |
no. 2 X
38.80m + no. 3 X 70m |
no. 2 X
38.80m + no. 3 X 70m |
|
Pirrera |
217.60m
+ 147.60m |
no. 2 X
38.80m + no. 2 X 70m |
no. 2 X
38.80m + no. 1 X 70m |
|
Di
Giorgio |
2 X 105m |
no. 1 X
70m + no. 2 counterweights of 17.5m |
no. 1 X
70m + no. 2 counterweights of 17.5m |
|
Ficuzza |
2 X
147.60m |
no. 2 X
38.80m + no. 1 X 70m |
no. 2 X
38.80m + no. 1 X 70m |
|
Fontanazza |
2 X
601.40m |
no. 2 X
50.70m + no. 5 X 100m |
no. 2 X
50.70m + no. 5 X 100m |
|
Buzza |
2 X
1101.40m |
no. 2 X
50.70m + no. 10 X 100m |
no. 2 X
50.70m + no. 10 X 100m |
|
Pagliaro |
2 X
357.60m |
no. 2 X
38.80m + no. 4 X 70m |
no. 2 X
38.80m + no. 4 X 70m |
|
Chiappe |
2 X
147.60m |
no. 2 X
38.80m + no. 1 X 70m |
no. 2 X
38.80m + no. 1 X 70m |
|
Caronia |
2 X 634m |
no. 2 X
47m + no. 6 X 90m |
no. 2 X
47m + no. 6 X 90m |
|
Portale |
2 X
370.10m |
no. 2 X
50.05m + no. 3 X 90m |
no. 2 X
50.05m + no. 3 X 90m |
|
Ledera |
2 X
280.10m |
no. 2 X
50.05m + no. 2 X 90m |
no. 2 X
50.05m + no. 2 X 90m |
|
Canneto |
433.05m
+ 370.10m |
no. 1 X
50.05m + no. 3 X 90m + no. 1 X 90.50 + no. 1 counterweight of 22.50m |
no. 2 X
50.05m + no. 3 X 90m |
|
Petraria |
2 X
370.10m |
no. 2 X
50.05m + no. 3 X 90m |
no. 2 X
50.05m + no. 3 X 90m |
|
Ortora |
2 X
370.10m |
no. 2 X
50.05m + no. 3 X 90m |
no. 2 X
50.05m + no. 3 X 90m |
|
Gebbiole |
2 X
217.60m |
no. 2 X
38.80m + no. 2 X 70m |
no. 2 X
38.80m + no. 2 X 70m |
|
S.
Stefano |
2 X
432.50m |
no. 1 X
50m + no. 4 X 90m + no. 1 counterweight of 22.50m |
no. 1 X
50m + no. 4 X 90m + no. 1 counterweight of 22.50m |
|
Maccarone |
2 X
147.60m |
no. 2 X
38.80m + no. 1 X 70m |
no. 2 X
38.80m + no. 1 X 70m |
|
Tusa |
2 X 820m |
no. 2 X
50m + no. 8 X 90m |
no. 2 X
50m + no. 8 X 90m |
|
Cicero |
2 X
370.10m |
no. 2 X
50.05m + no. 3 X 90m |
no. 2 X
50.05m + no. 3 X 90m |
|
Buongiorno |
2 X
427.60m |
no. 2 X
38.80m + no. 5 X 70m |
no. 2 X
38.80m + no. 5 X 70m |
|
Lardino |
1 X
287.60m |
no. 2 X
38.80m + no. 3 X 70m |
- |
|
Milianni |
820m +
460m |
no. 2 X
50m + no. 8 X 90m |
no. 2 X
50m + no.4 X 90m |
|
S.
Biagio |
1 X
147.60m |
no. 2 X
38.80m + no. 1 X 70m |
- |
|
Pollina |
2 X
1152.50m |
no. 1 X
50m + no. 12 X 90m + no. 1 counterweight of 22.50m |
no. 1 X
50m + no. 12 X 90m + no. 1 counterweight of 22.50m |
|
Della
Marina |
357.60m
+ 217.60m |
no. 2 X
38.80m + no. 4 X 70m |
no. 2 X
38.80m + no. 2 X 70m |
Read more about the Messina - Palermo
Motorway :
·
Background
·
First Construction period
·
Second Construction period
·
Main Tunnels
|